Concept > FEED > Detailed Design
Project Phase
106 weeks
Project Duration
50,500
Hours of Engineering
Context
A Central European refinery wanted to take advantage of carbon taxation exemptions available for increasing the biocomponent content of hydrocarbons in its finished product.
The refinery had already maximised the amount of FAME (biodiesel) blended into its diesel product and bioethanol blended in its gasoline product. The next opportunity was the co-processing of renewable feedstocks, such as UCO and animal fats, through its diesel hydrotreater.
Challenge
The aim was for renewable feedstock to make up 5wt% of the total diesel hydrotreater feed.
Solution
InSite provided a multi-discipline team to support the refinery across different phases of the project, including concept studies, FEED, and detailed design. The project was executed in phases to ensure feasibility, cost-effectiveness, and risk mitigation.
TECHNICAL WORK
The project originally included a pre-treatment unit (PTU) to process the UCO before entering the hydrotreater. However, due to difficulty in sourcing feedstock for the PTU and economics, it was decided to outsource the pretreatment process and import pretreated feedstock to the refinery.
UCO Pre-treatment Unit Concept Study
- Optioneering study to identify existing equipment that could be repurposed.
- Development of the process flow scheme, heat & mass balance, and plot plan.
- Preparation of safety, environmental, and operating philosophies.
- Identification of pre-treatment vendor scope and interfaces.
- Civil & structural calculations and assessment for the pre-treatment unit.
- Provision of a HAZID chairperson and technical experts to review the project basis.
- Comprehensive class 5 Cost Estimate of several options, to assist the client in the phase gate approval.
UCO Pre-treatment Unit FEED and Detailed Design
- Design of the facilities outside of the pre-treatment unit, including tank refurbishment, new pump, pipework design, electrical supply, and control system integration.
- Civil design for the pre-treatment unit, including new tankage/silos and access routes.
- Mechanical design support for the pre-treatment unit.
- Provision of project management support at the client site and Vendor management for the pre-treatment unit.
UCO Co-processing Concept Study
- Identification of suitable tie-in points and existing equipment that could be repurposed.
- Preliminary design of the truck and rail unloading facilities.
- Review of filtration and heating requirements.
- Investigation of water wash options to minimise corrosion.
- Preparation of process simulations to enable a heat & mass balance to be prepared and to review possible options for improved heat integration.
- Updates to P&IDs and attendance at HAZOP.
- Preparation of +/-30% cost estimate.
Corrosion Mitigation Overview
- Addressed HCl corrosion by implementing water-wash injection facilities to dilute the acid and bring the pH back into a less corrosive range.
- Conducted calculations of salt sublimation temperature to determine locations where NH4Cl salts could form and implemented water wash facilities at these points.
Challenges & Lessons Learned
- Corrosion
Specialised refinery experience was essential in identifying and mitigating corrosion issues. - Uncertainty of UCO feedstock chlorine content
The project found a balance between feedstock variability and Capex.
- Reuse and refurbishment of equipment
Site experience was crucial in identifying existing equipment that could be reused and refurbished.
KEY ACHIEVEMENTS
InSite achieved several significant outcomes:
- Successfully identified and implemented a cost-effective solution for UCO processing.
- Enabled the refinery to increase biocomponent content, contributing to carbon taxation exemptions.
- Developed detailed technical solutions for corrosion mitigation and process optimisation.
- Provided valuable engineering and project management support, ensuring the successful execution of project phases.









